The Ohio State University Medical Center photo

Project Profile - Pneumatic Tube System ReplacementThe Ohio State University Wexner Medical Center

  • 15,000 LF of New 6″ Tubing
  • Project Value: $5.5 Million
  • Synergent Services:
    • Pre-Design Feasibility Review
    • Construction Administration
    • Owner’s Representation / Project Management
    Synergent Contributions:
    • Facilitated cost reduction initiatives
    • Administered two (2) prime contractors
      • Documented Weekly Progress Meetings
      • Resolved field conflicts
      • Documented daily progress
      • Managed changes to the contract
      • Managed pay application process
      • Negotiated contract disputes
    • Reworked the schedule mid-project and maintained original end dates when the Owner determined that 2/3 of the remaining project must be done on nights and weekends.
    Scope of Project (2012-2013)
    • Demolition of Existing 4” Pneumatic Tube System
    • Installation of New 6” Pneumatic Tube System
    • Sixty (60) Pneumatic Tube Stations
    • 15,000 Lineal Feet of New Pneumatic Tubing
    • Renovations in Active Nursing Stations
    Key Synergent Consultants:

ATS Implementation Planning & Support

The Ohio State University Medical Center
ATS Benchmark Since 2004

The Ohio State University Medical Center photo

Carnegie/89th Street Garage & Service Center

Cleveland Clinic
Project Value: $192 million

Cleveland Clinic - photo

Central Sterile Supply Department

The Ohio State University Medical Center
Project Value: $7.2 million

The Ohio State University Medical Center photo
Our consultants approach their work within the context of the challenges facing your hospital, not from a predefined set of templates.

We listen.

We perform.

We deliver.

Find Us

Mailing Address:
9446 Haaf Farm Court
Pickerington, Ohio 43147

info@synergentllc.com
(614) 286-0258